NHDOT Hooksett Road Paving Project Update

This update is provided as of June 12, 2024
  • Traffic loops are being installed this week (These are the buried electrical lines under the pavement at intersection approaches that magnetically alert the signal system that vehicles have arrived at the intersection to turn the light green).
  • The loops will not be done in time to pave the area by the Shaw’s Plaza this week, so that paving will be done at night next week.
  • The roadway shoulder gravel material will be installed next week.
  • The paving required to tie in driveways and side streets (such as Pleasant Street) will be installed next week.
  • Line Stripping and Thermo Patching will be installed next week.  The thermos markings are labor intensive and will take a week to complete (These are arrow symbols, crosswalks and other symbols at intersections).
  • A pedestrian signal pedestal will be installed next week at the intersection of Rt. 3 and Londonderry Turnpike.  This will be installed after the thermos crosswalk is installed.
  • The de-mobilizing process will be in two weeks.
  • It is expected that the project will be 99% complete by July 4th.